Hi experts,
When we use lot-sizing procedures PK, I have a problem about it.
Can you please kindly help me.
The problem is.
When we run MRP and get the release date as past date in purchase requisition.
I would not like system to propose release date as past date.
Do we need more configuration for using lot-sizing procedures PK ?
The settings are mentioned as below.
* material master
- Lot size in MRP1 view : PK
- MRP Type in MRP1 view : PD
- Procurement type in MRP2 view : F
* MRP parameters
- Processing key : NETCH
- Create purchase req. : 1 (Purchase requisitions)
- Delivery schedules : 3 (Schedule lines)
- Create MRP list : 1 (MRP list)
- Planning mode : 1 (Adapt planning data (normal mode))
- Scheduling : 2 (Lead Time Scheduling and Capacity Planning)